Jakarta, Sanda-id.com - PT Metropolitan Tollroad will again carry out road maintenance work at Toas Tol Padaleunyi.
General Manager Representative Office 3 Metropolitan Jasamarga Tollroad Thomas Manatmanto explains, the maintenance job will begin at 22-26 August 2022.
"Clan services are always committed to keeping their quality and street service, especially safety and street security factors. For that routine maintenance like SFO and reconstruction of culture is always done periodically,
Marga Services ensures that the line becomes a street maintenance object temporarily cannot be met during work.
"The Clan apologies for the inconvenience caused by the work. Be advised to street users to remain cautious and set the time of travel. Contact one call center Marga Services at 1408 phone number for information and toll aid," said Thomas
As for the work schedule of Ruas Tol Padaleunyi as follows:
A. Reconstructuring Work
Reconstruction work at the Padaleunyi Toas, will take place 22- 26 August 2022, starting at 08.00-14.
Location
- Cileunyi direction
Km 142 + 066 to Km 142 + 131 Line 1, length 65 meters and Km 142 + 179 to Km 142 + 214 Line 1, length 35 meters. - Jakarta direction
Km 127 + 383 to Km 127 + 343 Line 1, length 40 meters, and Km 127 + 420 to Km 127 + 395 Line 1, length 25 meters.
B. Scrapping Filling Overlay (SFO) job
SFO's work will be done on August 225, 0800-1700.
Location
- Cileunyi direction
- On / Off Ramp@@
- On / Off Ramp@@
C. Marka strike job
Street strike work at the Padaleunyi Toas, will take place 22- 26 August, 08.00 - 1700 pm.